2002 the then TVA Board approved goal to restart Browns Ferry Nuclear
Unit 1. TVA estimated it would cost $501 Million as reported by GAO in approving TVA debt reduction plan
in 2004. "The restart of the Browns Ferry Unit 1 nuclear plant in Alabama, taken off line in 1985, is getting
closer, much closer, as the $1.8 billion renovation nears completion." May 4, 2007
TVA: Browns Ferry Nuclear Plant 1 Gets Go Ahead
Nuclear Brownout: TVA’s Browns Ferry Nuclear Power Plant from Green Scissors
An overloaded computer network prompted an emergency shutdown in a reactor at the Tennessee
Valley Authority BF 3.
Browns Ferry Restart Would Needlessly Gouge Consumers by Public Citizen (5/15/07)
Safety System Fails at Restarted Unit 1 The Decatur Daily 5/30/07

NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-259, 50-260, and 50-296]
Tennessee Valley Authority; Browns Ferry Nuclear Plant; Final Environmental Assessment and Finding of No
Significant Impact Related to the Proposed License Amendment To Increase the Maximum Reactor Power Level